Complex challenges:

  • Poor ground conditions during winter months.
  • Enabling works to continue in peat soils during winter by managing the water table on site with a temporary holding pond and dewatering into the Awakeri channel.
  • Design and the construction of recharge pits within narrow berm spaces.
  • Preloading of platforms and monitoring movement of preload.

Location

180 Walters Road

Size

Stage 1: 6 lots, 0.1815ha
Stage 2: 49 lots, 2.1022ha

Client

Walter Estate Ltd

Schedule

February 2019 – August 2019 (Earthworks Contract Only), Civil Works Stage 1 due to commence on EPA approval.