Grove Road Residential Development

Slider image
Slider image
Slider image
Slider image
Slider image
Slider image
Slider image
Slider image

Project details

Residential Subdivision

Complex challenges:

  • Poor ground conditions during winter months.
  • Enabling works to continue in peat soils during winter by managing the water table on site with temporary holding ponds.
  • Minimising sediments entering the live swale channel along Walters Road.
  • Preloading of platforms and monitoring movement of preload.

Location

135 Grove Road

Size

76 lots, 2.01ha

Client

Lefon Development Ltd

Schedule

January 2019 – October 2019 (Earthworks Contract Only), Civil Works due to commence on EPA approval.